| Hint | Explanation | Answer | % Correct |
|---|---|---|---|
| Critical Path | If an activity on the critical path is delated then the planned completion date will be impacted. Activities on the critical path have no float. | the path through activities giving the earliest completion date | 73%
|
| Terminal float | When determining the appropriate amount of terminal float, a contractor will look at the risks associated with going over the allocated programme deadline | The difference at the end of a project between the contracted completion date and the contractor's planned completion date | 64%
|
| Activity float | 'spare time' within an activity. created by rounding up the time required for a task | 45%
| |
| Free Float | the maximum time by which the completion of a task can exceed its earliest finish time without affecting the earliest start times of the succeeding tasks | 36%
| |
| Total Float | the maximum time by which the completion of a task can exceed its earliest finish time without affecting the project duration | 36%
| |
| Float | A measure of flexibility of tasks | the amount an activity can be delayed or prolonged without adverse affect on activities | 27%
|