Float - Statistics

General Stats
  • This quiz has been taken 29 times
  • The average score is 3 of 6
Answer Stats
Hint Explanation Answer % Correct
Critical Path If an activity on the critical path is delated then the planned completion date will be impacted. Activities on the critical path have no float. the path through activities giving the earliest completion date
73%
Terminal float When determining the appropriate amount of terminal float, a contractor will look at the risks associated with going over the allocated programme deadline The difference at the end of a project between the contracted completion date and the contractor's planned completion date
64%
Activity float 'spare time' within an activity. created by rounding up the time required for a task
45%
Free Float the maximum time by which the completion of a task can exceed its earliest finish time without affecting the earliest start times of the succeeding tasks
36%
Total Float the maximum time by which the completion of a task can exceed its earliest finish time without affecting the project duration
36%
Float A measure of flexibility of tasks the amount an activity can be delayed or prolonged without adverse affect on activities
27%