| Question | Answer | % Correct |
|---|---|---|
| Force Majeure (eg epidemic) | Time | 90%
|
| Exceptionally adverse weather conditions | Time | 80%
|
| Civil commotion / terrorism | Time | 80%
|
| National strikes | Time | 80%
|
| Inaccurate descriptions / forecasting of the works by approx quantities | Money | 60%
|
| Variations to the works | Both (depending on what it is) | 50%
|
| Delays from nominated sub contractor | Time | 50%
|
| Discrepancies in tender docs | Money | 40%
|
| Failure to provide contractor relevant goods/materials | Money | 30%
|
| Delays in receiving information | Money | 30%
|
| CDM issues | Money | 30%
|
| Changes in statutory requirements | Time | 30%
|
| Failure to provide contractor possession and/or access to site | Money | 20%
|
| Discovery of antiquities on site | Money | 20%
|