| Hint | Answer | % Correct |
|---|---|---|
| What does EMV stand for in risk analysis? | Expected Monetary Value. | 100%
|
| How much float does a task on the critical path have? | Zero | 100%
|
| What is Risk Acceptance? | Acknowledging the risk and setting aside a contingency fund to pay for it if it happens. | 0%
|
| What does ACWP stand for? | Actual Cost of Work Performed (the real money spent so far). | 0%
|
| What is an Excusable Delay? | A delay caused by the client; the contractor gets extra time and financial compensation. | 0%
|
| What is an Inexcusable (Culpable) Delay? | A delay caused by the contractor; no extra time, no extra money, and potential penalties apply. | 0%
|
| What is an Elemental Cost Plan? | A multi-rate method that breaks down building costs by major physical components (elements). | 0%
|
| What is a Neutral Delay? | An "Act of God" (like extreme weather); the contractor gets an Extension of Time (EOT) but no extra money. | 0%
|
| What is a "Top-Down" or "Single-Rate" estimating method? | A quick estimating method used in early stages when detail is low. | 0%
|
| How must a "Function" be described in VE? | As an active Verb + Noun (e.g., "Support Building", "Exclude Weather"). | 0%
|
| What is the Unit of Accommodation Method? | A single-rate method that multiplies the cost of one functional unit (like a student bedroom) by the total number needed. | 0%
|
| What is the definition of Value Engineering (VE)? | : A systematic method to improve the "value" of a project by analyzing the function of its elements. | 0%
|
| What is the formula for Cost Variance (CV)? | BCWP - ACWP. | 0%
|
| What is the formula for Schedule Variance (SV)? | BCWP - BCWS. | 0%
|
| What is the main purpose of a WBS? | break the project scope down into manageable, deliverable-oriented components. | 0%
|
| What does BCWP stand for? | Budgeted Cost of Work Performed (also known as Earned Value). | 0%
|
| What does BCWS stand for? | Budgeted Cost of Work Scheduled (the planned value of work we expected to finish by today). | 0%
|
| What does a "Design Development Risk" allowance cover? | Costs arising from incomplete design information or coordination gaps. | 0%
|
| What does an "Employer Change Risk" allowance cover? | Costs arising from potential scope changes requested by the client during construction. | 0%
|
| What does a "Construction Risk" allowance cover? | Costs arising from site conditions, weather, and poor productivity. | 0%
|
| What is the formula for calculating the Value Index (VI)? | Cost ÷ Worth. | 0%
|
| What is Resource Levelling? | Delaying tasks to meet strict resource limits, which will extend the final project duration. | 0%
|
| What is Risk Avoidance? | Eliminating the risk entirely by changing the project plan or design. | 0%
|
| What does EOT stand for? | Extension of Time. | 0%
|
| What visual tool is used to trace a problem backward to its fundamental root cause? | Fault Tree Analysis. | 0%
|
| What is the Critical Path? | he longest sequence of dependent tasks that determines the shortest possible project duration. | 0%
|
| What are the four main types of construction resources? | Human (Labour), Material, Machinery (Plant/Equipment), and Financial. | 0%
|
| Name two sustainability/programme benefits of switching a concrete frame to a timber frame. | Lower embodied carbon and faster on-site erection. | 0%
|
| What does OBS stand for? | Organizational Breakdown Structure. | 0%
|
| What is the formula for calculating BCWP? | Percentage Complete (PC) × Budget at Completion (BAC). | 0%
|
| What is the formula for calculating Expected Monetary Value (EMV)? | Probability (%) × Impact Cost. | 0%
|
| What visual chart shows the peaks and troughs of daily resource demand? | Resource Histogram. | 0%
|
| What matrix combines the WBS and OBS to assign roles? | Responsibility Assignment Matrix (RAM). | 0%
|
| What are the three core steps of Risk Management? | Risk Identification, Risk Analysis, and Risk Response. | 0%
|
| What is Resource Smoothing? | Shifting tasks within their available float to flatten resource peaks without delaying the project end date. | 0%
|
| What is Risk Transfer? | Shifting the financial impact of the risk to a third party (e.g., using a fixed-price contract or insurance). | 0%
|
| Name the three major building elements that usually make up 80% of a project's cost. | Structure, Envelope, and MEP Services (Mechanical, Electrical, Plumbing). | 0%
|
| What is Resource Aggregation? | Summing up the daily resource requirements based on the schedule. | 0%
|
| What is Risk Mitigation? | Taking active steps to reduce either the probability or the impact of a risk | 0%
|
| What is the Pareto Principle in construction estimating? | The 80/20 rule; roughly 80% of project costs are tied up in just 20% of the building's elements. | 0%
|
| What is Float | The amount of time a task can be delayed without delaying the final project completion date | 0%
|
| What does a Value Index (VI) greater than 1.20 indicate? | The element costs over 20% more than its functional worth, making it a prime candidate for VE. | 0%
|
| In the Last Planner System, who are the "Last Planners"? | The people at the workface making daily/weekly decisions (foremen, trade supervisors, subcontractors). | 0%
|
| If your Schedule Variance (SV) is a negative number, what does it mean? | The project is behind schedule. | 0%
|
| If your Cost Variance (CV) is a negative number, what does it mean? | The project is over budget. | 0%
|
| According to NRM1, how should a project manager determine the size of a contingency fund? | Through systematic risk analysis, rather than just adding an arbitrary flat percentage. | 0%
|
| What is the primary goal of the Last Planner System? | To make reliable short-term commitments and stabilize the workflow. | 0%
|
| Traditional scheduling focuses on what "should" be done. What does Lean Collaborative Planning focus on? | What "can" be done by removing constraints early. | 0%
|