Hint
|
|
Answer
|
|
What does CDM stand for
|
|
Construction design and management regulations
|
|
If a project is notifiable, who submits notice
|
|
Client/Employer
|
|
A project is notifiable if it is expected to last more than __ days and have more than __ workers working simultaneously
|
|
30 20
|
|
Or if its expected to involve more than ___ person days
|
|
500
|
|
What does RIDDOR stand for
|
|
Reporting of injuries, diseases and dangerous occurrences regulations
|
|
What is a hazard
|
|
Anything that may cause harm
|
|
What is a risk
|
|
The chance that somebody could be harmed by the hazard and how serious that harm would be
|
|
What must be reported and records kept of under RIDDOR. WRDe WRDi RI DO
|
|
Work related deaths work related diseases Reportable Injuries Dangerous Occurences
|
|
Name statutory documentation CPP, HaSF, N, PCI
|
|
Construction phase plan health and safety file Notification Preconstruction information
|
|
What actually is a DO (im not telling you the answer to the other question)
|
|
Incidents with the potential to cause harm
|
|
Name the 5 necessary welfare facilities SC, WF, CRaL, DW, FfR.
|
|
Sanitary Conveniences Washing Facilities Changing Rooms and Lockers Drinking Water Facilities for Rest
|
|
HSE enforce CDM. Who are they
|
|
Health and Safety Executive
|
|
A ______ _______ is a statement by an inspector, that is accepted in writing by the duty holder, that the duty holder has committed an offence for which there is a realistic prospect of conviction
|
|
Simple caution
|
|
An ___________ ______ specifies the remedial action and gives the duty holder a date by which they must complete the action
|
|
Improvement notice
|
|
A ___________ ______ tells the duty holder to stop an activity immediately to prevent serious personal injury
|
|
Prohibition notice
|