| Hint | Answer | % Correct |
|---|---|---|
| If a project is notifiable, who submits notice | Client/Employer | 100%
|
| What does CDM stand for | Construction design and management regulations | 100%
|
| HSE enforce CDM. Who are they | Health and Safety Executive | 100%
|
| A project is notifiable if it is expected to last more than __ days and have more than __ workers working simultaneously | 30 20 | 0%
|
| Or if its expected to involve more than ___ person days | 500 | 0%
|
| What is a hazard | Anything that may cause harm | 0%
|
| Name statutory documentation CPP, HaSF, N, PCI | Construction phase plan health and safety file Notification Preconstruction information | 0%
|
| An ___________ ______ specifies the remedial action and gives the duty holder a date by which they must complete the action | Improvement notice | 0%
|
| What actually is a DO (im not telling you the answer to the other question) | Incidents with the potential to cause harm | 0%
|
| A ___________ ______ tells the duty holder to stop an activity immediately to prevent serious personal injury | Prohibition notice | 0%
|
| What does RIDDOR stand for | Reporting of injuries, diseases and dangerous occurrences regulations | 0%
|
| Name the 5 necessary welfare facilities SC, WF, CRaL, DW, FfR. | Sanitary Conveniences Washing Facilities Changing Rooms and Lockers Drinking Water Facilities for Rest | 0%
|
| A ______ _______ is a statement by an inspector, that is accepted in writing by the duty holder, that the duty holder has committed an offence for which there is a realistic prospect of conviction | Simple caution | 0%
|
| What is a risk | The chance that somebody could be harmed by the hazard and how serious that harm would be | 0%
|
| What must be reported and records kept of under RIDDOR. WRDe WRDi RI DO | Work related deaths work related diseases Reportable Injuries Dangerous Occurences | 0%
|