Traditional or Design and Build - Statistics

General Stats
  • This quiz has been taken 38 times
    19 since last reset
  • The average score is 8 of 10
Answer Stats
Question Answer % Correct
Design and construction are integrated Design and Build
100%
Contractor does design Design and Build
100%
Buildability can be full incorporated into the design Design and Build
100%
Employer only has to enter into one contract Design and Build
100%
Contractor is responsible for design delays Design and Build
100%
Construction can begin before design is complete Design and Build
100%
Employer has less influence in design Design and Build
100%
Contractor has few, if any, design obligations for permanent works Traditional
100%
Design is complete by the time the contractor is selected Traditional
100%
Slower overall Traditional
100%
More difficult for employer to make changes Design and Build
86%
Higher tender price to account for more risk Design and Build
80%
Design organisation appointed first with appropriate form of design contract Traditional
75%
Reasonable certainty of final project cost at time of tender Traditional
75%
Employers design requirements are fully understood and options can be explored by the designers Traditional
75%
Delays to design decision or changes to drawings after contract award are employers liability Traditional
75%
Project requirements detailed in contractor's brief Design and Build
60%
Difficult to compare tenders Design and Build
60%
Longer tender period Design and Build
50%
Does not assist team working Traditional
50%
Designer acts as contract administrator during the construction process Traditional
25%
Frequent misunderstanding of tender documents Traditional
25%
Statutory approvals which require early design work can be obtained Traditional
0%