50 Planning, Estimating and Cost Management.

Quiz by
MChan
Rate:
Last updated: May 4, 2026
You have not attempted this quiz yet.
First submittedMay 4, 2026
Times taken1
Average score4.2%
Report this quizReport
60:00
Enter answer here
0
 / 48 guessed
The quiz is paused. You have remaining.
Scoring
You scored / = %
This beats or equals % of test takers also scored 100%
The average score is
Your high score is
Your fastest time is
Keep scrolling down for answers and more stats ...
Hint
Answer
What is the main purpose of a WBS?
break the project scope down into manageable, deliverable-oriented components.
What does OBS stand for?
Organizational Breakdown Structure.
What matrix combines the WBS and OBS to assign roles?
Responsibility Assignment Matrix (RAM).
What is the Critical Path?
he longest sequence of dependent tasks that determines the shortest possible project duration.
What is Float
The amount of time a task can be delayed without delaying the final project completion date
How much float does a task on the critical path have?
Zero
What are the four main types of construction resources?
Human (Labour), Material, Machinery (Plant/Equipment), and Financial.
What is Resource Aggregation?
Summing up the daily resource requirements based on the schedule.
What visual chart shows the peaks and troughs of daily resource demand?
Resource Histogram.
What is Resource Smoothing?
Shifting tasks within their available float to flatten resource peaks without delaying the project end date.
What is Resource Levelling?
Delaying tasks to meet strict resource limits, which will extend the final project duration.
What does BCWS stand for?
Budgeted Cost of Work Scheduled (the planned value of work we expected to finish by today).
What does BCWP stand for?
Budgeted Cost of Work Performed (also known as Earned Value).
What is the formula for calculating BCWP?
Percentage Complete (PC) × Budget at Completion (BAC).
What does ACWP stand for?
Actual Cost of Work Performed (the real money spent so far).
What is the formula for Schedule Variance (SV)?
BCWP - BCWS.
If your Schedule Variance (SV) is a negative number, what does it mean?
The project is behind schedule.
What is the formula for Cost Variance (CV)?
BCWP - ACWP.
If your Cost Variance (CV) is a negative number, what does it mean?
The project is over budget.
What is an Excusable Delay?
A delay caused by the client; the contractor gets extra time and financial compensation.
What is an Inexcusable (Culpable) Delay?
A delay caused by the contractor; no extra time, no extra money, and potential penalties apply.
What is a Neutral Delay?
An "Act of God" (like extreme weather); the contractor gets an Extension of Time (EOT) but no extra money.
What does EOT stand for?
Extension of Time.
What visual tool is used to trace a problem backward to its fundamental root cause?
Fault Tree Analysis.
Traditional scheduling focuses on what "should" be done. What does Lean Collaborative Planning focus on?
What "can" be done by removing constraints early.
In the Last Planner System, who are the "Last Planners"?
The people at the workface making daily/weekly decisions (foremen, trade supervisors, subcontractors).
What is the primary goal of the Last Planner System?
To make reliable short-term commitments and stabilize the workflow.
What is a "Top-Down" or "Single-Rate" estimating method?
A quick estimating method used in early stages when detail is low.
What is the Unit of Accommodation Method?
A single-rate method that multiplies the cost of one functional unit (like a student bedroom) by the total number needed.
What is an Elemental Cost Plan?
A multi-rate method that breaks down building costs by major physical components (elements).
Name the three major building elements that usually make up 80% of a project's cost.
Structure, Envelope, and MEP Services (Mechanical, Electrical, Plumbing).
What is the definition of Value Engineering (VE)?
: A systematic method to improve the "value" of a project by analyzing the function of its elements.
How must a "Function" be described in VE?
As an active Verb + Noun (e.g., "Support Building", "Exclude Weather").
What is the formula for calculating the Value Index (VI)?
Cost ÷ Worth.
What does a Value Index (VI) greater than 1.20 indicate?
The element costs over 20% more than its functional worth, making it a prime candidate for VE.
What is the Pareto Principle in construction estimating?
The 80/20 rule; roughly 80% of project costs are tied up in just 20% of the building's elements.
Name two sustainability/programme benefits of switching a concrete frame to a timber frame.
Lower embodied carbon and faster on-site erection.
What are the three core steps of Risk Management?
Risk Identification, Risk Analysis, and Risk Response.
What is Risk Avoidance?
Eliminating the risk entirely by changing the project plan or design.
What is Risk Transfer?
Shifting the financial impact of the risk to a third party (e.g., using a fixed-price contract or insurance).
What is Risk Mitigation?
Taking active steps to reduce either the probability or the impact of a risk
What is Risk Acceptance?
Acknowledging the risk and setting aside a contingency fund to pay for it if it happens.
According to NRM1, how should a project manager determine the size of a contingency fund?
Through systematic risk analysis, rather than just adding an arbitrary flat percentage.
What does a "Design Development Risk" allowance cover?
Costs arising from incomplete design information or coordination gaps.
What does a "Construction Risk" allowance cover?
Costs arising from site conditions, weather, and poor productivity.
What does an "Employer Change Risk" allowance cover?
Costs arising from potential scope changes requested by the client during construction.
What does EMV stand for in risk analysis?
Expected Monetary Value.
What is the formula for calculating Expected Monetary Value (EMV)?
Probability (%) × Impact Cost.
Save Your Stats
Your Next Quiz
How many countries do you know? In this quiz, you've got 15:00 to name as many as you can. Go!
Name all 50 states in the USA. Easy, right?
Can you name the capitals cities of all 196 countries in the world?
20 random countries have been removed from the map of the world! Can you identify them in 3 minutes?
Comments
No comments yet