Critical Path
If an activity on the critical path is delated then the planned completion date will be impacted. Activities on the critical path have no float.
Terminal float
When determining the appropriate amount of terminal float, a contractor will look at the risks associated with going over the allocated programme deadline
Float
A measure of flexibility of tasks
Free Float
Total Float
Activity float
'spare time' within an activity. created by rounding up the time required for a task
the amount an activity can be delayed or prolonged without adverse affect on activities
The difference at the end of a project between the contracted completion date and the contractor's planned completion date
the maximum time by which the completion of a task can exceed its earliest finish time without affecting the earliest start times of the succeeding tasks
the maximum time by which the completion of a task can exceed its earliest finish time without affecting the project duration
the path through activities giving the earliest completion date
Save Your Stats
Your Next Quiz
Name all 50 states in the USA. Easy, right?
The easiest of our continental map quizzes.
Can you name the countries with the most heavy metal bands, both in total and per capita?
Name the countries from which the greatest number of refugees have fled.
Comments
No comments yet